Indonesia’s China-Backed Rail Link Hit by New Hiccups

The path to Indonesia’s new high-speed rail service, built and funded with Chinese aid, has been drawn-out and bumpy, and now there are tussles over when it should open and loan fees


China-funded rail project in Indonesia faces fresh problems.
An electric high-speed train is seen during a test run in Tegalluar in West Java island in this Reuters image.

 

A high-speed rail link built and funded by China on Indonesia’s main island is the subject of a new dispute.

The China-funded consortium behind the $7.3-billion rail link – a flagship project for President Joko Widodo – wants the 142km (88 miles) line from capital Jakarta to the large city of Bandung to start full commercial operations in August.

But Indonesia’ transport ministry and three consultants oppose the move, an internal document has revealed.

The project, which is part of China’s Belt and Road scheme and being built by Indonesian and Chinese state firms, is already $1.2 billion over its initial budget and four years behind schedule.

Months before its proposed launch in August, the showpiece project is beset by fresh problems, with the consortium’s Chinese participants wanting a full operational worthiness certificate for the line despite an incomplete station, a 48-page presentation on the project shows.

However, Transport ministry officials and consultants Mott MacDonald, PwC and local law firm Umbra would prefer that full-fledged commercial operations start in January 2024, the “Progress Update” report dated May 14 shows.

“There is a risk that the target of commercial operations in August could be delayed to complete all construction by December 31,” said the report, written in the local language.

ALSO SEE:

Indonesia Keen to Sign Trade Deal With US on Key Minerals

 

Split over fee for additional $560m loan

A smooth opening of the railway line, the most high-profile BRI project in Southeast Asia’s largest economy, as part of Independence Day celebrations would be a shot in the arm for the ruling party ahead of a general election next year, analysts said.

“A further delay will only become ammunition for the opposition to attack,” said Teuku Rezasyah, an international relations analyst at Padjadjaran University, adding that setbacks would taint China’s credibility to develop and deliver big projects in the region.

But financial restructuring at PT Wijaya Karya Tbk (WIKA) – an Indonesian state-owned construction firm with an indirect minority stake in the consortium – is also hitting the working capital needs of the project, which has already accumulated at least $381.75 million in outstanding payments, another internal document shows.

WIKA corporate secretary Mahendra Vijaya said the company had the financial capacity to finish the remaining work, but it also needed the consortium to pay it for work already done.

Indonesia is negotiating with China on an additional $560 million loan and asking for an interest rate of 2.8% for the portion of the loan in yuan, which is lower than the China Development Bank (CDB) offer of 3.46%, according to a second set of documents dated May 18.

The possibility of a further delay and other details in the two documents have not been previously reported.

Septian Hario Seto, a senior official with the investment coordinating ministry, said debt negotiations were underway with CDB, focused on the interest rate.

 

Trial runs expected in August

The railway plans to begin further free trials with passengers in mid-August, with paid trips expected in September and the incomplete station likely finished by November, he added.

PwC declined to comment. China-backed consortium PT KCIC, Mott MacDonald, Umbra, CDB and China’s embassy in Jakarta did not respond immediately to requests for comment.

The fresh loan is needed to help cover the $1.2-billion cost overrun.

PT KCIC was awarded the project in 2015 after lodging a cheaper proposal than a Japanese rival, with completion expected in 2019. But the project has been plagued by delays due to land ownership disputes, questions over its economic impact and the Covid-19 pandemic.

Delays and cost blowouts are not uncommon in high-speed rail projects globally, including in Western countries.

 

Four decades till it becomes profitable

PT KCIC expects it will take 40 years for its investment to become profitable, twice as long as initial estimates, an executive said last year.

One-way tickets on the line will cost up to 350,000 rupiah ($23.56) depending on the distance travelled, according to PT KCIC, nearly a quarter of the average Indonesian’s weekly income.

The planned 45-minute train ride between Jakarta and Bandung compares with a car journey of two to three hours or the current three-hour rail trip.

But with the terminal stations located outside the city centres, the high-speed rail line could struggle to attract the business passengers being targeted, said Sutanto Soehodho, a transportation analyst at the University of Indonesia.

“They value time and seek convenience,” he said. “But if they need to transit again, why should they use it?”

Locating the stations in central Jakarta and Bandung would have been too costly, ministry official Seto said.

 

  • Reuters with additional editing by Jim Pollard

 

ALSO SEE:

 

China’s Belt & Road Costs ‘Soared to $240bn Amid Bailouts’

 

Indonesia Looks to Boost its EV industry With New Incentives

 

China’s JD.com to End Services in Thailand, Indonesia

 

Coal Mining in Indonesia Driving Forest Loss – China Dialogue

 

Indonesia Confirms Tesla Talks as Gigafactory Plan Rumoured

 

China’s Belt & Road Project ‘Facing Mounting Opposition and Debts’

 

Jim Pollard

Jim Pollard is an Australian journalist based in Thailand since 1999. He worked for News Ltd papers in Sydney, Perth, London and Melbourne before travelling through SE Asia in the late 90s. He was a senior editor at The Nation for 17+ years.

logo

AF China Bond